PO - Product backlog
User stories - Team - Acceptance criteria
DOR - definition of Ready
- Estimation - Relative
0, 1,2 ,3 ,5, 8,13, 21
User stories1 : Login - 1
US2 - Listing - 3
US3 - API integration - 21
- Credit card
- Debit card
-Net banking
- Paytm
US4 - Summary of trans - 5
US 5 - delivery tracking - 13
Backlog refinement meeting
--------------------------------
Sprint planning Meeting:
2 parts
1. Selection of user stories
2. Split - Task
--------------------
2 week sprint
10 days
Sprint1: 3 user stories - 3+8+5 = 16 = velocity
Sprint 2 :
US1 - 3
Task 1 - Mem1
Task 2 - Mem2
US2 - 2 - Half completed
US3 - 8
US4 - 5
-----------------
sprint 3:
Us5 - 13
US2 - 2 - Half completed
- Completed features are demoable - Split 1,1
- Next sprint
Velocity - Carry forward